Hand Dug Wells – The
Basics
Rural communities have frequently employed
hand-dug wells to provide a supply of water for individual use. Using
simple construction techniques and suitable materials, hand-dug wells can
provide reliable sources of water and offer the following advantages:
·
The equipment needed is light
and simple and thus suitable for use in remote areas.
·
The construction techniques are
easy for an unskilled worker to learn.
·
With the exceptions of cement
and reinforcing rods, the necessary materials are usually locally
available, making it one of the cheapest methods of well construction.
On the other hand, hand-dug wells present
certain limitations:
·
200 feet is usually the
practical limit of depth that can be reached, although most dug wells
are less than 65 – 70 feet deep.
·
Construction
is slow.
·
Extracting large quantities of
water with motorized pumps is not always feasible due to lack of
electricity.
·
Hard rock is very difficult to
penetrate and often can only be accomplished by blasting, which is slow,
hard work.
·
Because it is difficult to
penetrate very far into the aquifer, slight fluctuations in the water
table often make hand-dug wells unpredictable and unreliable.

For sanitation
reasons a pump is desirable. If installed on a hand-dug
well with a
full cover, a pump will help reduce chances of contamination
significantly. In rural areas where pump maintenance and repair can be a
real problem, large diameter wells are often the best solution to water
supply problems. Pumps can be installed while leaving an access way
through which water can be drawn by rope and bucket if the pump should
break down.
Compared to other well sinking methods, digging
a well by hand takes a long time. An organized and experienced
construction team consisting of five workers plus enough people to lower
and raise loads in the well can dig and line 3 feet per day in relatively
loose soil that does not cave in. However, the bottom section is likely to
take 2 or 3 days per foot because of the difficulty working while water
continually enters the well.
Depending on how you plan to develop the well,
the top section can take anywhere from a day or two to several weeks. An
experienced team sinking a 70 foot well and installing pulleys on the top
structure could easily take 5 weeks, including occasional days off (this,
of course, assumes no major delays). A new or inexperienced group would be
expected to take twice that time.
Hand-dug wells should be dug during the dry
season when the water table is likely to be at or near its lowest point.
The well can be sunk deeper with less interference from water flowing into
it. The greater depth should also ensure a year-round supply of water.
If the well cannot be dug during the dry season,
plan to go back to it at the end of the dry season to deepen it.
Plan your work
- Below are the major steps involved in digging
a well.
·
Choose a well site based on
geological factors, user preference, sanitary conditions, and
accessibility.
·
Determine available expertise -
people (including yourself) with well or general construction
experience.
·
Assess materials available -
tools, cement, reinforcement rods (re-rods), pre-cast liners, sand,
gravel, and wood.
·
Select methods of construction
that are most suitable for the use and available materials, considering
shape, size, depth, lining, bottom, and top.
·
Before construction begins, put
down in writing the work plan for the construction of the entire well.
·
Gather all equipment and
materials needed for construction of the well at the well site. Arrange
these at the site so as to facilitate construction as much as possible.
·
Lay out the hole with provisions
for checking diameter and plumb.
·
Arrange for people and materials
to get in and out of the well.
·
Dig and line the middle section.
·
Continue the digging and lining
procedure until you reach water, or some obstruction causes you to
change digging/lining procedure or abandon this well and pick a new
site.
·
Dig and line the bottom section
as far as possible into the aquifer. The method used to dig and line the
bottom section will often be different from the digging and lining
method used in the middle section. This may be necessary because you are
not only concerned with digging, lining, and possible hole collapse (as
in the middle section), but also with removing enough water from the
well to permit work to continue.
·
Install a simple sand and gravel
filter or porous concrete plug across the bottom of hole.
·
Extend the lining up above
ground to form the head wall.
·
Build and install the well
cover.
·
Install the pump in the cover on
the well.
·
Disinfect the well.
·
Build the apron (platform)
around the head wall to channel the run-off to one particular place.
Design your well -
To design a well, it is necessary to decide what
materials will be used and how they will be put together. This includes
determining:
·
The size and shape of the hole.
·
Preferred digging and lining
methods.
·
How much water needs to be
available, and, therefore, how deep the bottom section should go into
the aquifer.
·
How the top section should be
constructed to best protect the well from contamination, while allowing
easy access to the water.
·
The anticipated well depth.
Decisions to make?
Well Shape -
The shape of the well is what it would look
like if you were looking straight down into it.
Well Size -
The size of the well is a measure of how wide it is. Some holes are very
large, and some are very small. The size will be largely determined by:
(1) the way it is excavated, (2) the materials used to line it, and (3)
the purpose of the well.

The size of the
round hole is usually expressed by its
diameter, a meas
urement
from one edge of the hole through the midpoint
of the well to
the other side of the circle.
Diameter is the longest measurement across the
hole.
Although wells can be dug in any shape, almost
all wells are round. The reason for this is that a round well produces the
greatest amount of water for the least amount of work. Also, a round
lining is the strongest that can be built for the smallest quantity of
materials. Thus, while other well shapes have been used without problems,
a round shape enables the builder to get the most from available time,
money, and materials.
Square
or rectangular wells are usually dug where materials to be used in lining
the well necessitate such a shape. This is most often the case when flat
wood boards are the only lining materials available. Wood, however, is not
recommended.
Many factors could determine which diameter should be used.
·
Pre-cast lining sections come in
specific diameters. Choose your well diameter based on the available
size of Pre-cast lining sections.
·
Generally, the choice of
diameter will be based on two considerations. The well should have (a)
the smallest diameter which still provides (b) a comfortable working
space for the number of people that will be working in the well at one
time.
The smaller the diameter of the well, the less
soil and rock will have to be dug and fewer materials will be required to
line the well. Remember, if you double the diameter of the well, you
increase the amount of soil and rock that must be dug by four times.
The workers will need enough space so that they are not hampered in their
work. There must be enough space for them to use their tools and for the
bucket which will remove excavated materials from the well. Without enough
space, they will continually bump into each other and the wall.
During stages of its construction, a well may
have two or sometimes three different diameters. 
(i.e. The hole is dug to the diameter decided
upon. When a lining is installed, the diameter is reduced along with the
available working space. You may be installing the bottom section lining
inside the existing lining. This will further reduce the diameter.)
Ground Conditions and Lining - It is very difficult to anticipate
what the final depth of a well will be before it is begun. However, if
there are other wells in the area, it is possible to get an idea of the
approximate depth of the water table. This can be a great help when
gathering the materials needed for the lining construction.
All wells, except those drilled through rock,
can be expected to cave in with time unless a lining is installed to
support the well. The lining thus helps to keep the well open. There are
certain acts of nature, such as earthquakes or even gradual ground shifts,
which will break even the strongest linings, but these cannot be planned
for or anticipated.
Occasionally slight ground shifts can put
pressure on linings causing them to split and separate if not strongly
built. If no such information is available, it is recommended that you
build the lining strong enough to withstand normal earth stresses.
Depending on ground conditions, you may or may
not be able to dig the complete hole and then line it. In very loose sandy
soil, for example, the sand from the walls of the hole will frequently
cave into the hole, seriously hampering efforts to deepen the hole. There
are often relatively simple methods of dealing with such problems.
Designing the lining for the middle section is largely a matter of
assessing the ground conditions and materials availability to determine
the lining materials and method most appropriate for the situation.
Ground Conditions
·
Very loose soil (example: dry
sand) - the hole is as wide as the hole is deep because its sides
continually collapse and cave in.
·
Loose soil (example: damp sand)
- a relatively shallow (3 to 15 foot) hole can be dug before its sides
may cave in.
·
Firm soil (example: compacted
clay and sand mix) a hole can be dug to the water table with minimal
danger of collapse and cave in.
Unless you have had substantial experience
digging in the area and this particular type of soil, or have been trained
in the identification of soils and their properties do not leave the hole
unlined for more than 15 feet.
The only possible advantage to digging the
entire hole first is that you can then be certain that water can be
reached before you start using your often expensive materials to line the
well. However, if there is any question about the safety of working in an
unlined section of the well, it is not worth the gamble to leave it
unlined.
Dig a short section and line -
One source has suggested that for safety
reasons, no more than 15 feet of a well should be dug and left unlined.
More commonly, this cautious method is used in loose soil. This means of
construction is also recommended in all soils when workers are
inexperienced. Using this method, wells are dug in 2 to 15 foot sections,
and then lined.
Dig to water table and line -
This method is commonly used in firm soil,
especially where the water table is not very deep. It has the previously
mentioned advantage of not using any expensive materials in a well until a
good supply of water can be assured. However, this method should not be
attempted by workers inexperienced with well work.
Dig complete well and then line -
This method is not recommended because of the
danger of cave-ins beneath the water table which would undermine the
entire well shaft. The only situation in which this method might be
justified is where the middle section lining must rest on the bottom
section lining for support, but there are many ways of avoiding that
necessity.
Design the top section - The purpose of the top section is to
provide safe and easy access to well water and to prevent as much
contaminated surface materials as possible from entering the well.
The design of the top section is strongly influenced by two aspects of
well usage: (1) access to water or how water is drawn from the well and
(2) preventing surface contaminants from entering the water.
These two functions are not always compatible. It is often necessary to
compromise sanitation for the sake of water access. A top section, in
fact, is not absolutely necessary for the function of a well. However, the
different design of the parts of the top section is intended to make the
well safer, cleaner, and more convenient for users.
Major
components of the top section:
·
Head wall
·
Drainage apron (platform)
·
Cover
Head wall -
A head wall should be built on all wells which will not be fitted with a
permanent cover and a pump as a simple inexpensive safety feature which
will prevent people and animals from accidentally falling in.
This is simply a
wall which extends above the surface of the ground far enough to prevent
most accidental entry of people, particularly children, and animals. Its
external dimension is dependent on how thick you want the head wall to be.
The easiest and
best way to construct the head wall is as an extension of the lining. In
most cases it will be convenient to build the head wall as an extension of
the lining above ground. You will already have the equipment and supplies
on site with which to do this.

Drainage apron (platform) - A drainage apron is most often a
reinforced concrete slab 3 to 4 feet wide which surrounds a well and,
because of its slight slope, channels surface water away from the well.
Wire mesh reinforcing may be used if it is available.
By forcing water
to flow away from the well, the apron serves two functions:
·
It prevents contaminated surface water from following the
outside of the lining and flowing back down into the well before it has
had a chance to be sufficiently filtered by the earth.
·
It prevents the formation of a mucky area immediately
around the well which can be a source of contaminants to the well water.
A sloping platform
will simply move the mucky area from direct contact with the
head
wall to the edge of the platform.
By installing a
shallow channel,


or a
very short wall
around the edge of
the platform, the water can be funneled off to one specific area away from
the well where people and animals will not have to track through it to get
to the well.
The apron should
be strongly and carefully constructed as it will receive a lot of wear,
and any cracks or chips which develop will decrease the effectiveness of
the apron.
An apron can be
built of stone with mortared joints. If for some reason it is not feasible
to build an apron, dirt should be built up around the well so that water
spilled will tend to run off away from the well rather than collect around
it.
The Cover -
A cover can improve the sanitary quality of the water in the well by
preventing the dust and dirt normally carried in the air from entering and
contaminating the water. It also prevents people from dropping things into
the well.
There are two
basic variations of well covers, temporary (removable) and permanent
(fixed in place).
·
A temporary cover is one that covers the well between the
times it is being used, but must be removed to pull water from the well.
For example, a temporary cover would be a wooden cover that rests on top
of the well but must be removed to throw a bucket, tied to a rope, into
the well. This is a limited step toward protecting the well water from
surface contamination.
·
A permanent cover is usually made of reinforced concrete.
It can be poured in place on the well or pre-cast in one or more pieces
and later set over the well. Pump mounting bolts and an access door can
be cast into the concrete. Pre-casting the cover in one or two pieces
may be easier because of the difficulty of building a form which is both
strong enough to support the weight of the concrete over the open well
and which can then be removed after the concrete has set.
Design The
Bottom Section - There are two basic methods for constructing the
bottom section – sink the lining and dig-and-line.
1. Sink lining
into place. Advantages include:
·
The method protects workers from cave-ins during sinking;
·
Workers in the well can put all their effort into removing
soil and water, presumably allowing greater well penetration into the
aquifer.
A disadvantage is
the possibility that workers may have difficulty in firmly attaching the
rings together.
2. Dig and then
line. Advantages include:
·
The method requires less special preparation;
·
The bottom section lining attaches directly to the lower
part of the middle section lining, thus producing a stronger, continuous
structure.
The disadvantages
include:
·
Workers probably cannot get as far into the aquifer as in
the other method because of the necessity for workers to remove soil and
water and place reinforcing rod and concrete at the same time;
The purpose of the
bottom section is to allow as much water as possible into the well without
permitting any of the fine soil particles from the surrounding aquifer to
enter the well.
There are three
commonly used methods of allowing water to enter the well.
·
Through porous concrete linings - Lining rings sunk into
the bottom section can be made of porous concrete which acts as a filter
to prevent soil particles from entering the well.
·
Through angled holes in the lining - Holes can be punched
in a freshly poured concrete ring which, when cured, can be sunk into
the bottom section. These holes are more effective at preventing soil
entry if they are slanted up toward the middle of the well.
·
Through the bottom - The bottom of the well should always
be constructed to allow water to come up through it. Often the bottom is
simply left open and uncovered but it is preferable to prevent soil
entry and the gradual filling up of the well.

The final step
– is to disinfect your well in order to kill harmful bacteria or other
organisms that may have been introduced during the construction process.
Disinfecting is necessary after well completion, pump installation, and at
any time the system is opened for repair or maintenance.
FYI:
Deeper Wells
are generally less vulnerable to contaminations from local surface
activities. The water in deep wells probably traveled a considerable
distance underground.
Shallow Wells
usually draw from the groundwater nearest the land surface, which may be
directly affected by farmstead activities. Rain and surface water soak
into the soil and can carry pollutants with it.
Local Geology determines the length of time for pollutants to
contaminate well water. In some places, this process happens quickly -
less than one year. Areas with thin, sandy soil cover or cracked and
exposed bedrock are particularly vulnerable. On the other hand, thick clay
soils absorb some pollutants. This may delay - but not prevent - the day
when a well "turns bad".
If you want to learn about ALL of it - pumps,
wells, and so on...

Cottage Water Systems: An Out-Of-The City Guide to Pumps, Plumbing, Water Purification, and Privies

Top of page